  • 1, before using the first check: power first press the switch, then with the knife, check whether the operation is flexible. Vibrator, roller operation, dialing stick operation is normal. Wire rope in the reel on the winding situation; out of the hoisting platform, etc. are normal. If the fault is found, notify the electromechanical team to deal with. After handling, before use.
  • 2, a feeding not too much, according to the ratio of feeding, pay attention to water-cement ratio. Stir evenly, a mixing time of not less than a minute, the normal mix of concrete, should be very thick porridge.
  • 3, fixed hand boot, the driver should be familiar with the operating principle of the operating system, found that the failure immediately check.
  • 4, electrical parts should be care, cable to protect, to prevent damage.
  • 5, the mixer should be pad flat, mixer funnel can not stand, to prevent the funnel falling water when wounding.
  • 6, temporary stop, should be regular (every twenty minutes), start the mixer, to prevent concrete coagulation or concrete pour out the drum, rinse the drum with water.
  • 7, concrete watering after the shutdown, should be promptly the drum and the machine outside the mortar washed with water clean. Into the hopper under the cleanup of each class, so that when the material into the provisions of the decentralization of the party, and in the appearance of a layer of oil, to be used next time.
  • 8, seriously implement the shift system, the work of the machine to work, pay attention to matters clearly.